Bitcoin miner Riot Platforms has entered a 20-year agreement to supply 191 megawatts of power from its Rockdale, Texas, facility to Anthropic, according to the company and a Bloomberg report. The deal could generate $9 billion (roughly Rs. 85,806 crore) in value and further accelerates the shift among Bitcoin miners towards AI infrastructure. Riot expects the initial deployment to begin in December 2027, with the full build-out scheduled for June 2028.